Milestones
· September 1993 -- investment license granted
· September 1994 -- ground breaking ceremony
· March 1995 -- piling work started
· August 1995 -- piling of main power house completed
· October 1995 -- chimney construction work started
· January 1996 -- all Piling Work Completed
· march 1996 -- boiler installation
· March 1997 -- #1 Unit Installation Completed
· February 1998 -- #1 unit commissioned
· July 1998 -- all three units commissioned
· December 2000 -- ISO 9002 certificate received
. October 2009 -- Natural Gas commissioned with all three units
. January 2010 -- ISO 9000 - 2008 certificate received
|